SMED (single minute of Exchange OF those, dt.: Tool change within the one-digit minute range) marks a procedure, which is to reduce the preparation time of a production machine. A goal is it, without disturbing the manufacturing river to reequip the machine on a new manufacturing process.

Was developed the procedure of Shigeo Shingo, which as external advisors considerably in the development Toyota of the production system (TPS) was involved.

Conversion: In several iterative steps the preparation time is improved by organizational measures. Larger investments become, if at all, only at a very late time transacted.

Substantial element during the conversion is it to divide preparation procedures into internal and external steps.

  • Internal steps can be accomplished only with stop of the machine (e.g. tool change)
  • External steps can be accomplished, if the machine still (e.g. supply of the tools and Vorprodukte) produces.

SMED runs off in four steps:

  • Separation from internal and external preparation procedures
  • Transfer of internal into external preparation procedures
  • Optimization and standardisation of internal and external preparation procedures
  • Removal of adjustment procedures

These steps are repeated gone through, until the preparation time lies in the one-digit minute range.

For optimization different techniques are used, e.g.:

  • Use of clamps instead of screws
  • Sliding tables instead of cranes
  • separate preheating
  • Intermediate tighteners for adjustment outside of the machine
  • Parallelism of preparation procedures - simultaneous instead of successively - i.e. instead of, several coworkers use
  • Elimination of adjustments
  • Mechanization
  • Standardisation of preparation activities

Advancements of the SMED procedure are:

  • Zero Changeover: Re-equipment within three minutes
  • OTED (= One Touch Exchange OF): Reequip by an arm movement

See also

  • Toyota production system
  • Slim management
  • one piece flow

Related links


Related Websites

We found here 2 related websites.

Page cached: piątek, maj 25, 2012 21:33:26
Valid XHTML 1.0!  Valid CSS!

Page copy protected against web site content infringement by Copyscape